Interstate Area Street/Utility Improvements

The City Council awarded the project to S.R. Weidema, Inc. Phase 1 was completed fall of 2019, and construction for phases 2 and 3 began in April 2020.  Construction is complete with the exception of various punch list items.  The Contractor is required to provide a warranty on all work for one year from the date of acceptance of the project.

Thanks to all of you for your patience and understanding throughout this process!  It is our hope and intent that the improvements in the neighborhood, combined with previous, existing and future improvements throughout the City, will provide a strong and healthy long-term economic base for the entire City and will renew a sense of community and neighborhood pride.

           
Project Details
Full street reconstruction with concrete curb and gutter
Partial Storm sewer replacement
Sanitary sewer replacement
Partial water main replacement

Contact Information
Please contact the following for all of your project coordination issues and information.

                       

Utility Outages
Please contact the following:
  • CenterPoint Energy (gas leak): 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • City of Brooklyn Center 7 am to 3:30 pm: 763-585-7100
    • Water
    • Sanitary 
    • Storm Sewer
    • Street Lighting
    • Or Traffic Signal Systems
  • After hours call 911 (the dispatcher will contact the appropriate on-call service staff)
  •            
                                                         
    Project Schedule

    October 24, 2018 - Neighborhood informational meeting held

    November 12, 2018 - City Council to receive feasibility report

    December 10, 2018 - City Council to conduct public hearing, authorize the project and order preparation of plans and specifications

    February 25, 2019 - City Council to approve plans and specifications and authorize the advertisement for bids
                   
    May 31, 2019 - Bid Opening

    June 10, 2019 - Project Award

    June 17, 2019 - Preconstruction Meeting

    June 2019 - East of Camden (Start of Construction)

    October 2019 - East of Camden (End of Construction)

    April 2020 - West of Camden (Start of Construction)

    October 2020 - West of Camden (End of Construction)
                   
                                           
                     



    Project Area Map website COMPRESSED.jpg
                     Enlarge Map

                   
    Project Information
    Project History Page
           
                   

    Newsletters
    March 2020
    April 2020
    May 2020
    June 2020
    August 2020
    September 2020
    October 2020


    Construction Updates
    March 13, 2020
    April 16, 2020
    April 22, 2020
    April 29, 2020
    May 7, 2020
    May 21, 2020
    May 27, 2020
    June 10, 2020
    June 25, 2020
    July 16, 2020
    August 20, 2020