Click to Home
Resident Help Center

Go To Search
Evergreen Park Area Reconstruction Project
Project Update
At its meeting on March 27, 2017, the City Council awarded the project to Ryan Contracting Company of Elko, Minnesota. A neighborhood meeting was held at the Water Treatment Plant, 7110 Camden Avenue N on April 6, 2017, at which time residents had the opportunity to ask questions and meet with City staff and the Contractor. Construction has started and construction updates and monthly newsletters (please see right side) will be added to this site throughout the project.        


Project Details
Full street reconstruction with concrete curb and gutter
Storm sewer replacement
Sanitary sewer replacement
Partial water main replacement
           

Contact Information
Please contact the Inspectors/Project Engineer for all of your project coordination issues and information at 763-569-3340 or .
  • Jay Hill, Project Inspector
  • Alex Rakos, Project Inspector
  • Trevor Williams, Project Inspector
  • Mike Albers, Project Engineer

Utility Outages
Please contact the following for utility outages:            
  • CenterPoint Energy (gas leak): 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • City of Brooklyn Center (water, sanitary, storm sewer, street lighting, or traffic signal systems)
    7:00 a.m. to 3:30 p.m.: 763-585-7100
    After hours call 911 (the dispatcher will contact the appropriate on-call service staff)

                

                       


           











           






                                                                 
             Evergreen project area map.jpg
                                 Enlarge Map
           
                                                       
Project Information            
Assessment Map

Project History 

Neighborhood Preconstruction Meeting Flyer 

           
Construction Updates
April 14, 2017
April 21, 2017
May 9, 2017
May 30, 2017
June 21, 2017
July 11, 2017
July 28, 2017
                

Newsletters
April
May

                       


        





           







           







Project Schedule
October 12, 2016 - Neighborhood informational meeting held

October 24, 2016 - City Council received feasibility report, declared costs to be assessed and calls for public hearing

November 28, 2016 - City Council held public hearing, authorized the project and ordered preparation of plans and specifications

January 23, 2017 - City Council approved plans and specifications and authorizes the advertisement for bids

March 2017 - Bid Opening and City Council to award contractor
           
April 2017
- Start project construction
                       
October 2017 - Anticipated construction substantially complete