Palmer Lake West Reconstruction Project
Project Update
Kuechle Underground, Inc. continues to move forward with the project.  For current project information, please view the weekly construction update.  A monthly newsletter will also be mailed to residents/property owners informing them of the projects progress. 


Project Details
Full street reconstruction with concrete curb and gutter
Storm sewer replacement
Sanitary sewer replacement
Partial water main replacement


Contact Information
Project Management Team
Please contact the Project Manager/Inspectors for all project coordination issues and information.

     • Jay Hill, Project Inspector: 763-569-3332 or

     • Alex Rakos, Project Inspector: 763-569-3323 or

     • Mike Albers, Project Manager/Engineer: 763-569-3326 or
               
           
Utility Outages
Please contact the following for utility outages:            
  • CenterPoint Energy (gas leak): - 612-372-5050
  • Xcel Energy (electric outage): 1-800-895-1999
  • CenturyLink: 1-877-348-9007
  • Comcast: 1-800-934-6489
  • Signal Systems: Todd Berg 763-585-7102
  • City of Brooklyn Center (water, sanitary sewer, storm sewer, street lighting or traffic signal systems)
    7:00 am to 3:30 pm - 763-585-7100
  • After hours - call 911 (the dispatcher will contact the appropriate on-call service staff)   
           


           
           
           
                                   






           




           
           

           



           

 



   





               




                







































                        
PLW Project Area Map.jpg
               Enlarge Map 
          
                             
Project Information    
Assessment Map

Project History
 
Staging Map
                          
                            
Construction Updates
April 14, 2016
April 20, 2016
April 27, 2016
May 4, 2016
May 12, 2016
May 18, 2016
May 25, 2016
June 1, 2016
June 8, 2016
June 15, 2016 
June 21, 2016
July 6, 2016 
July 13, 2016
July 21, 2016
July 29, 2016
August 5, 2015      
August 9, 2016
August 24, 2016
September 7, 2016
September 16, 2016
September 21, 2016
September 28, 2016
                       
Newsletters
       
April Newsletter
May Newsletter                     
June Newsletter
July Newsletter
August Newsletter
September Newsletter
November Newsletter
                                                                        
       
           



Project Schedule
October 27, 2015 - Neighborhood informational meeting held

November 9, 2015 - City Council receives feasibility report, declares costs to be assessed and calls for public hearing

December 14, 2015 - City Council holds public hearing, authorizes the project and orders preparation of plans and specifications

January 11, 2016 - City Council approves plans and specifications and authorizes the advertisement for bids

April 7, 2016 - Start project construction

October 2016 - Anticipated construction substantially complete