63rd Avenue Reconstruction Project
Project Update
Construction is complete with the exception of various punch list items.  The Contractor is required to provide a warranty on all work for one year from the date of acceptance of the project.

Thanks to all of you for your patience and understanding throughout this process!  It is our hope and intent that the improvements in the neighborhood, combined with previous, existing and future improvements throughout the City, will provide a strong and healthy long term economic base for the entire City and will renew a sense of community and neighborhood pride.
Project Details
Full street reconstruction with concrete curb and gutter
Complete Storm sewer replacement
Complete Sanitary sewer replacement
Complete Water main replacement
Contact Information

Project Management
Please contact the following for all of your project coordination issues and information:
Mike Albers, Project Manager/Engineer - 763-569-3340 or
Frank Brodeen, Project Inspector
SRF Consulting Group, Inc. - Assisted with construction administration and staking.
Utility Outages
Please contact the following for utility outages:
  • CenterPoint Energy gas leak - 612-372-5050
  • Xcel Energy electric outage - 1-800-895-1999
  • CenturyLink - 1-877-348-9007
  • Comcast - 1-800-934-6489
  • City of Brooklyn Center (water, sanitary sewer, storm sewer, street lighting, or traffic signal systems) 7:00 am to 3:30 pm - 763-585-7100
    After hours - call 911 (the dispatcher will contact the appropriate on-call service staff)





          63rd Avenue Area Satisfaction Survey
Click here!                           

63rd project area map_thumb.jpg 
                         Enlarge Map
Project Information
Project History           

Assessment Map

Construction Updates
May 22, 2015
June 8, 2015
June 18, 2015
June 25, 2015               
July 2, 2015

May Newsletter
June Newsletter
July Newsletter
August Newsletter
September Newsletter
November Final Newsletter