Freeway Park Area Reconstruction Project
Project Update
Construction is complete with the exception of various punch list items. The Contractor is required to provide a warranty on all work for one year from the date of acceptance of the project.

Thanks to all of you for your patience and understanding throughout this process!  It is our hope and intent that the improvements in the neighborhood, combined with previous, existing and future improvements throughout the City, will provide a strong and healthy long term economic base for the entire City and will renew a sense of community and neighborhood pride.
Project Details
Full street reconstruction with concrete curb and gutter
Storm sewer replacement
Sanitary sewer replacement
Partial water main replacement

Contact Information
Project Management Team
Please contact the project manager/inspector for all project coordination issues and information.                                 **Loucks Associates will be assisting with construction administration and staking.

Utility Outages

Please contact the following for utility outages:            
  • CenterPoint Energy gas leak - 612-372-5050
  • Xcel Energy electric outage - 1-800-895-1999
  • CenturyLink - 1-877-348-9007
  • Comcast - 1-800-934-6489
  • City of Brooklyn Center (water, sanitary sewer, storm sewer, street lighting, or traffic signal systems) 7:00 am to 3:30 pm - 763-585-7100
          After hours - call 911 (the dispatcher will contact the appropriate on-call service




Freeway Park Project Area Map_thumb.jpg
                           Enlarge Map

Project Information
Assessment Map   

Project History                         
Staging Map      

Construction Updates
May 12, 2015
May 21, 2015
May 26, 2015
June 8, 2015
June 18, 2015
June 25, 2015
July 1, 2015
July 8, 2015                     
May Newsletter
June Newsletter
July Newsletter
August Newsletter
September Newsletter
November Newsletter
April 2016 Newsletter


Project Schedule
November 2014 - Neighborhood information meeting to be held

December 2014 - City Council receives feasibility report, declares costs to  be assessed and calls for public hearing

January 2015 - City Council holds public hearing, authorizes the project and orders preparation of plans and specifications

March 2015 - City Council approves plans and specifications and authorizes the advertisement for bids

May 2015 - Start project construction

October 2015 - Construction substantially complete